Ledwood Mechanical Engineering


steelwork for the North Wales wind farm site at Gwynt y Mor.

Ledwood have recently been awarded a contract to manufacture and supply transport and support steelwork for the North Wales wind farm site at Gwynt y Mor. .......more


Replacement of No. 4 Blast Furnace

LMEL are pleased to announce the recent contract award by Tata Steel Strip Products Limited for the procurement, fabrication and erection of the main furnace pipe work for the .......more


Total Lindsay Oil Refinery

Ledwood have recently completed a successful T&I at Total's oil refinery. Initially contracted in November 2010 to develop methodology and plan for their T&I in September 2011. Our team of experts reviewed the scope of works and presented the client with .......more


Quality Incentive Award

Fluor are delighted to report that this month we presented the projects first monthly Quality Incentive Award. Decembers award being presented to Derek Edwards and Wayne Williams of Ledwood mechanical engineering LTD .......more


Appointment of Corporate Health & Safety Manager

Rees Davies has proudly joined LMEL taking the post of Corporate H&S Manager after recently working for a leading national multi discipline contractor as a Regional HSE Manager covering South and West Wales and Southern England.......more


New Heater Technology for Major Gas utility company

Ledwood are currently working with GL Noble Denton as part of a project to select new gas heaters for the Major Gas utility company distribution network. Ledwood has overall responsibility for the installation of the heaters and as well as overseeing the civil and electrical work,.......more


Ledwood awarded the RoSPA “Order of Distinction”in recognition of its outstanding health and safety record



Recent Projects

Project

  • BP Saltend - 2010

2.6 million pound contract to fabricate and deliver a steam methane reformer for Foster Wheeler, ultimate destination being BP's Hull refinery. The project comprised of 340 Tonnes of reformer, 180 Tonnes of structural steelwork, 100 Tonnes of transport steelwork, 800 linear meters of hand railing and 900 square meters of galvanised flooring. The project was fabricated over 3 key workshops and a dedicated refractory installation facility, workshop A handled the convection modules and steelwork, Workshop B fabricated and installed pipework. The Dockyard facility was utilized for construction of the 10 radiant modules.

  